This page contains a summary of the CASU management overview charts.


List of all the workpackages, responsibles and overview of timelines for VDFS pipeline project.
Note that V3 timeline section is not funded yet and is included solely for continuity of planning.

Summary of top level gantt chart.

Provisional project risk analysis and definition of terminology.

First quarter progress summary under workpackage spreadsheet task headings 2003 Q1 delivereds .

Second quarter deliverables using same nomenclature 2003 Q2 planned deliverables .

Open office presentation to specially convened AGOC on March 28th, also translated powerpoint version.
Contains among other things a summary of overall progress to date.