From j.p.emerson@qmul.ac.uk Fri Mar 28 17:21:19 2003 Date: Thu, 27 Mar 2003 19:16:13 -0000 From: Jim Emerson To: Peredur Williams , Mike Irwin Subject: risk register for future use VISTA's risk registers are in spreadssheets with the following column headings owner summary of risk details of risk progress area mitigation strategy impact (scale 1-5) likelihood (scale 1-5) exposure = impacct* likelihhod only risks with exposure >= 10 are actively discussed at present. We may as well do the same From ppt overheads............. Provisional risk assessment --------------------------- Risk P(r) impact contingency late delivery camera system/commissioning high med do V2 stuff recruitment delays in new hire med low temp hire development problems in new algorithms med med be smarter unforeseen detector peculiarities low high moan at WFCAM team we've been there hardware setup and delivery delays low high nah reprocessing for bug fixes med med allowed for keeping up with data volume med high gaps between obs (eg. data transfer problems) losing key staff to other lucrative jobs low high no chance